Change Proposal: CP1366

Data Quality Obligations for Outgoing Supplier Agents [Open]

Proposer Name: E.ON Energy Solutions Ltd

Current Phase: Approved

Category: SVA

Lead Analyst: David Kemp

Responsible Panel Committee: Supplier Volume Allocation Group (SVG)

Summary

One of the conclusions from Issue 41 – “Improving the Quality & Accuracy of Data Flows” was that there is little incentive on an outgoing Supplier or Agent to resolve issues (including co-operating with the other Suppliers or Agents or carrying out sometimes complex analysis) once they were no longer associated with that metering point.
CP1366 seeks to require Supplier Agents to be responsible for the quality of data, with respect to a Metering System, during their period of appointment; even if data quality issues are identified after the Agent’s de-appointment.

History

CP1366 was raised and issued for industry impact assessment via CPC00707 on 23 December 2011, with responses due back on 26 January 2012. The SVG approved CP1366 for inclusion in the June 2012 Release at its meeting on 3 April 2012.

Documents

CP1366 Approved Redlining to BSCP504  [215.1 Kb]
Event: CP1366 Approved Redlined Changes
Event Date: 3 April 2012

CP1366 Approved Redlining to BSCP514  [163.8 Kb]
Event: CP1366 Approved Redlined Changes
Event Date: 3 April 2012

CP1366 SVG Decision Paper (SVG134/02)  [173.5 Kb]
Event: CP1366 presented to SVG
Event Date: 3 April 2012

CPC00707 - Collated Responses for CP1366  [229.7 Kb]
Event: CPC00707 - Collated Responses for CP1366
Event Date: 20 January 2012

CPC00707 - CP1365 & CP1366  [568.6 Kb]
Event: CPC00707 Issued
Event Date: 23 December 2011

CP1366 Draft Redlining to BSCP504  [13.5 Kb]
Event: CP1366 Draft Redlined Changes
Event Date: 23 December 2011

CP1366 Draft Redlining to BSCP514  [16.0 Kb]
Event: CP1366 Draft Redlined Changes
Event Date: 23 December 2011

CP1366 Form  [33.5 Kb]
Event: CP1366 Raised
Event Date: 23 December 2011