Budget

This part of the Business Plan details the budgeted costs for 2020/21 in support of our strategy. This budget enables us to continue delivering our BSC obligations, allows us to implement our leading technology platform, increase our engagement with our stakeholders and customers, develop market arrangements, and focus on developing our people capabilities. All of this is necessary to allow us to support our customers and the changing market place.

Elexon is a not-for-profit entity, funded by electricity market participants. We do not carry any reserves or retained capital, and any underspend against budget is always returned to those participants. In light of this, budgeting for uncertainties in advance of any new financial year, with no other access to working capital, requires careful consideration. We need to put in place contingencies mindful of this constraint. We also endeavour to set challenging financial and efficiency targets for the business, which ensure we deliver the best possible value for money to the industry.

Table 01

Budget Summary
Item Year to
March
2019/20
Budget
£’000
Year to
March
2019/20
Forecast
£’000
Year to
March
2020/21
Budget
£’000
Variance
to
2019/20
Budget
£’000
Variance
to
2019/120
Budget
%
Year to
March
2021/22
Projection
£’000
Year to
March
2022/23
Projection
£’000
ELEXON Operational 23.2 22.9 24.4 (1.2) (5.4) 24.5 24.8
EMR Contribution (3.3)  (3.4)  (3.5) 0.2  (7.6)  (3.5)  (3.5)
Subtotal 19.9 19.5 20.9  (1.0)  (5.0) 21.0 21.3
Contracted Costs 18.0 17.3 20.1  (2.1)  (11.7) 21.8 21.8
Total Regular Activity 37.9 36.8 41.0  (3.1)  (8.2) 42.8 43.1
Demand Led Costs4 4.9 4.7 4.2 0.8 15.3 4.4 4.4
System Strategy 9.9 4.6 10.1 (0.2) (2.1) 12.8 12.8
Market Development 0.5 0.5 0.5 0.5 0.5
Total Projects 15.3 9.8 14.8 0.5 3.5 17.7 17.7
OVERALL TOTAL 53.2 46.7 55.8 (2.6) (4.8) 60.5 60.8

The overall total budget to deliver BSC activity in 2020/21 is £55.8m, which represents an increase of £2.6m (4.8%) against the current year’s budget of £53.2m. Excluding the new service of Radio Teleswitching cost recovery of £1.4m (see further details below), the increase in budget is £1.2m (2.3%).

The budget increase anticipated in 2020/21 compared to the forecast for 2019/20 (£46.7m) is driven by the impact of the Foundation Programme and other factors, which are summarised below.

In 2018/19 Elexon developed a plan to deliver its Wider Access and TERRE commitments on Elexon’s new digital platform (the Foundation Programme).

In 2019/20, we have successfully progressed some of the core elements of the developments. Due to the substantial and complex deliverables needed to meet the Project TERRE requirements, we have had to prioritise regulatory changes, such as this over our systems strategy work, resulting in a lower spend in 2019/20.

As a result, during our mid-year budget review in September- October 2019, we returned £6.4m of used budget, mainly System Strategy budget (£5.3m), back to BSC Parties. However for 2020/21 we are budgeting to spend at the level that we set out in last year’s business plan.

The budget for total regular activity shows an increase of £1.7m (4.4%) against the budget for 2019/20. This increase excludes the new additional Radio Teleswitching costs of £1.4m. It follows the conclusion of the Issue 84 workgroup, where the industry agreed that the Radio Teleswitch Service operational costs (previously borne by ENA) will now be recovered through BSC from April 2020. This new arrangement will see these costs fully recovered from BSC Parties on an annual basis. We recognise that our customers have specific cost pressures (not least the retail price cap) and that the costs levied by Elexon for our services contribute to this. We have therefore strived to maintain our operational costs at existing levels, despite delivering improvements in service and dealing with an ever-changing energy system.

Within the budget, we account for services Elexon provides to its subsidiary, EMRS. Next year (2020/21) will be the sixth year that Elexon, in its role as Settlement Services Provider for EMR, delivers its services via EMRS to the LCCC and ESC. All EMR related costs are fully funded by LCCC and ESC and the total costs of LCCC and ESC (which include those of EMRS) are consulted on separately by BEIS. Our participation also enables us to offset some of our overheads, which would otherwise have been borne by BSC Parties (actual savings for 2018/19 are £726k), and are budgeted for 2020/21 at £1m.

Chart 1 above details the total costs of Elexon regular activity net of staff and overhead costs for EMR activities (which are fully funded by LCCC/ESC) since go-live of the New Electricity Trading.

Arrangements (NETA) in 2001/02. This is expressed in real terms (in 2019/20 money after applying April RPI of each year). It shows our success over the years in bringing costs down but also reflects that in recent years we have both invested in future proofing our central systems and increased our activities to support the evolving market and new business models, as well as to deliver innovation.

The budget for our operational costs for 2020/21 is £20.9m, 5% more than the current year budget, and includes costs such as people, occupancy, staff-related and administrative expenses, consultancy and legal support.

This also includes the contribution from EMR activities as a result of providing resources to our EMR subsidiary, EMRS for which it recompenses Elexon. BSC people costs are expected to increase by £647k (5.2%). This figure is derived by deducting the £249k EMR contribution from £896k in the ‘Variance to 2019/20 Budget’ column from Table 2.

Table 02

Elexon Operational Costs
Item Year to
March
2019/20
Budget
£’000
Year to
March
2019/20
Forecast
£’000
Year to
March
2020/21
Budget
£’000
Variance to
2019/20
Budget
£’000
Variance
to 2019/20
Budget %
Year to
March
2020/21
Projection
£’000
Year to
March
2022/23
Projection
£’000
People Costs 15,562 15,653 16,458 (896) (5.8) 16,712 17,010
Other Operational
Overheads
7.590 7,276 7,942 (353) (4.6) 7,784 7,796
EMR Contribution (3,262) (3,419) (3,511) 249 (7.6) (3.511) (3,511)
Operational Total 19,890 19,510 20,890 (1,000) (5.0) 20,985 21,295

The 2020/21 regular activity headcount remains consistent with the 2019/20 budget, with an increase of only 0.6 full time equivalents (FTE). The headcount illustrated in Table 3 is an average for the year and does not represent the actual number of persons. Instead, it represents a fulltime equivalent of those working directly for Elexon, and also contractors, and is, therefore, representative of the costs.

Table 03

Elexon Average Headcount
Headcount Year to March
2019/20
Budget
Year to March
2019/20
Forecast
Year to March
2020/21
Budget
Variance to March
2019/20
Budget
Variance to March
2019/20
Budget %
Year to March
2021/22
Projection
Year to March
2022/23
Projection
Average Employee Headcount 189.2 182.5 199.5 (10.3) (5.4) 200.1 200.1
Average Contractor Headcount 11.4 12.2 8.6 2.9 25.0 6.3 5.3
Average Total Headcount 200.6 194.7 208.0 (7.4) (3.7) 206.4 205.4
EMR Contribution (26.2) (27.3) (33.0) 6.8 (26.0) (33.0) (33.0)
BSC BAU Headcount 174.4 167.4 175.0 (0.6) (0.3) 173.4 172.4

We have budgeted based on known headcount by function, which is to remain static for the entire year. Full consideration is taken of indexation as well as employment conditions and trends in our sector, as well as the wider economy while preparing this budget. To allow for all of these potential costs, and in recognition that recruiting staff to fill vacancies created through natural turnover will sometimes require a modest uplift in salary, we have included a provisional amount in the 2020/21 budget, for this purpose. To fulfil our role as the EMR Settlement Service Provider, we have contracted with LCCC and ESC to provide the services on day rates that fully recover our management overheads, office overheads and occupancy costs on a not-for-profit basis in respect of those personnel working on EMR. We have budgeted 33 FTEs to deliver these services.

The £3.5m EMRS Contribution represents the income from LCCC and ESC to pay for EMRS, which is made up of people costs for those directly or partially used to deliver EMR services, as well as a share of fixed overheads apportioned on a per person basis. The fixed overheads element of the contribution defrays the fixed overheads that BSC Parties are currently paying, for example occupancy and the IT infrastructure, and is budgeted to be £1.0m for 2020/21.

A significant proportion of our costs of delivering the BSC arrangements come from contracted expenditure for the BSC Agents and contracted service providers for running legacy systems in parallel to the new technology platform until we can retire the legacy systems. We have adopted this parallel approach over a ‘big bang’ approach to reduce the risk and ensure that legacy systems are retired only once the new solution is stable. These are predominantly fixed costs, linked to indexation.

The key drivers of our £2.1m (16.3%) increase are as follows:

  • Radio Teleswitch Service (RTS) – Following discussions with Energy UK in July 2019, Elexon convened industry representatives to agree a solution for operational RTS costs to be recovered from BSC Parties post April 2020, through existing BSC cost recovery arrangements. This represents £1.4m of new BSC contracted costs.
  • Central Systems: During the transition period to the new digital platform we will run two systems in parallel to reduce risk. While some of the BSC Agents are still remaining on legacy infrastructure, running two systems gives rise to an increase of £1.3m. This is offset by no longer accounting for amortisation of assets from previous years, which has a budget impact of £0.7m

Table 04

Contracted Costs
Item Year to March
2019/20
Budget £’000
Year to March
2019/20
Forecast £’000
Year to March
2020/21
Budget £’000
Variance to
2019/20
Budget £’000
Variance to
2019/20
Budget %
Year to March
2021/22
Projection £’000
Year to March
2022/23
Projection £’000
Total Contracted 18,026 17,312 20,127 (2,100) (11,7) 21,846 21,780

 

To ensure that we are appropriately funded in order to implement changes requested by industry through BSC modifications, our budget has to incorporate an element of demand driven expenses (‘demand led’).

The budget for BSC systems releases is £3.9m. This is a decrease (17.2%) on the previous year’s budget. The budget incorporates scheduled BSC changes, notably TERRE, Market-wide Half-Hourly Settlement, Performance Assurance changes and a number of other approved BSC changes. The budgeted figures are based on the impact assessment of known modifications, taking into account estimates of historic change costs, as well as taking a view on new changes that may come forward during the year.

Table 05

Demand-led costs
Item Year to
March
2019/20
Budget
£’000
Year to
March
2019/20
Forecast
£’000
Year to
March
2020/21
Budget
£’000
Variance
to
2019/20
Budget
£’000
Variance
to
2019/20
Budget
%
Year to
March
2021/22
Projection
£’000
Year to
March
2022/23
Projection
£’000
IA – Modification Proposals 105 57 105 105 105
BSC Systems Releases 4,732 4,594 3,919 813 17.2 4,200 4,200
Panel Committee Projects 50 52 100 (50) (100.0) 100 100
PAF Review 37 30 46 (9) (23.9)
Total Demand Led 4,923 4,732 4,170 754 15.3 4,405 4,405

This area of our budget is entirely dedicated to fund our Foundation Programme, which is working to transform and transition the current ageing BSC Central Systems to deliver a new digital platform based on modern technologies. We have had to prioritise regulatory changes, such as TERRE over our systems strategy work resulting in a lower spend in 2019/20. However for 2020/21 we are budgeting to spend at the level that we set out in last year’s business plan.

The Platform will be easier to maintain, mitigate the risks of failure and deliver better value for money to BSC Parties, as well as greater flexibility for future market arrangements.

We have several releases planned for 2020/21 (as explained earlier in this plan). We have adopted a phased approach to delivering the Foundation Programme, to minimise the overall cost and risk to parties, whilst spreading the cost across several years to reduce the financial impact on BSC parties. As such, we have included a budget of £10.1m in 2020/21, which is in line with the 2019/20 budget provision of the Foundation Programme.

Due to Elexon’s funding model, the absence of retained capital and in accordance with allowable accounting treatment under accounting standard FRS102, we do not need to capitalise this investment. Due to the phased nature of this transformation, we do not believe that this will materially impact the profile of our charges to industry compared to a ‘big bang’ approach.

Table 06

System Strategy costs
Item Year to March
2019/20
Budget £’000
Year to March
2019/20
Forecast £’000
Year to March
2020/21
Budget £’000
Variance to
2019/20
Budget £’000
Variance to
2019/20
Budget %
Year to March
2021/22
Projection £’000
Year to March
2022/23
Projection £’000
System Strategy 9.9 4.6 10.1 (0.2) (2.1) 12.8 12.8

The budget for Market Development is £0.5m to allow us to cover any non-BAU activities regarding the developments within the GB energy market and is unchanged from 2019/20.

A number of industry developments remain that require Elexon to continue to monitor, engage and informally assess impacts outside of the formal change process. Some of those have been referred to earlier. We continue to engage with new market entrants and their proposed business models, seeking to ensure the BSC enables innovation. In addition to all of the activity outlined earlier, we have been aiding Ofgem in the development of the Retail Energy Code, sharing learnings from the BSC.

Table 07

Market Development
Item Year to March
2019/20
Budget £’000
Year to March
2019/20
Forecast £’000
Year to March
2020/21
Budget £’000
Variance to
2019/20
Budget £’000
Variance to
2019/20
Budget%
Year to March
2021/22
Projection £’000
Year to March
2022/3
Projection £’000
Market Development 0.5 0.5 0.5 0.5 0.5

This section outlines how we expect to charge the budget to BSC Trading Parties. Table 08 contains charging proposals from Section D of the BSC. Table 09 shows the charges excluding VAT.

The BSC Panel reviewed Section D charges in 2019/20 and found the charging regime is fit for purpose, reflective of the BSC parties’ activities and fair to existing and new market participants.

Table 08
Section D

  • £500 Application Fee
  • Membership fee of £250 per month
  • CVA Metering System Monthly Charge of £50 per month. CVA BM Unit Monthly Charge (other than for Supplier BM Unit) of £0 per month (this charge is levied on each pair of BM units in the case of an exempt generator);
  • For communication line and TIBCO charges, please refer to the Elexon website
  • Notified Volume Charge per Gross Contract MWh at a rate of £0.0005/MWh
  • For all Base SVA BM Units a charge of £0 per month
  • For all Additional SVA BM Units a charge of £60 per month has been made
  • SVA costs split:
    • 50 percent of costs are paid by generators on basis of metered energy volumes
    • A fixed fee of £0.00915 per SVA Metering System per month;
    • Remainder allocated on Suppliers Non Half Hourly MWh market share.
  • All remaining costs split on basis of metered energy volumes.

*These are based on the current charges.
Please refer to the BSC website for current rates.

Based on the information in Table 08 examples of charges to BSC Parties are provided in the following tables.

Table 09

Assumed split of costs

Firstly, the 2020/21 Annual Budget is set out in Table 09.

Item 2019/20
Budget
2019/20
Forecast
2020/21
Budget
Supplier Volume Allocation
(SVA) Costs
5.6 5.4 7.0*
Other Costs 47.6 41.2 48.8
Total 53.2 46.7 55.8

*SVA Costs increase because of the RTS Service costs, recovered from BSC Parties.

Table 10

Market Assumptions

Secondly, various assumptions about the size of the market are made. These are presented in Table 10.

Item 2019/20
Budget
2019/20
Forecast
2020/21
Budget
Number of Trading Parties 477 440 440
Sales – Notified Contract Volumes (TWh) 840 760 780
Purchases – Notified Contract Volumes (TWh) 840 760 780
Generation (TWh) 254 235 242
Supply (TWh) 251 230 237
Non Half Hourly (NHH) Supply (TWh) 130 104 107
HH Supply (TWh) 130 127 130
CVA BM Units 793 840 840
SVA Base BM Units 213 225 225
SVA Additional BM Units 145 185 185
Data Line 75 60 63
Comms Software (5 users) 29 29 29
Comms Software (additional user) 0
CVA Metering Systems (MSIDs) 936 924 925
HH Supply (MSIDs) 31,049,998 31,161,927 31,785,166

 

Table 11

Expected Charges

Thirdly, the charging regime from Section D of the BSC in Table 8 is then applied to costs in Table 9 based on the assumptions in Table 10. This gives the estimated charges (either specified charges or £/MWh fees) as shown in Table 11.

Charge Item 2019/20
Budget
2019/20
Forecast
2020/21
Budget
Specified Charges
CVA BM Units (£/month) 100 100
SVA Base BM Units (£/month) 100 100
SVA Additional BM Units (£/month) 60 60 60
Data Line – estimated average (£/month) 700 700 700
Comms Software – average quad2 processor (£/month) 1,080 1,080 1,080
Comms Software {additional user} (£/month) 22 22 22
Contract Traded (£/MWh) 0.0005 0.0005 0.0005
CVA Metering Systems (£/month) 50 50 50
Base Monthly Charge (£/month) 250 250 250
SVA
HH SVA Ops (£/MSID/month) 0.00632 0.00757 0.00918
NHH SVA Ops (£/NHH MWh)
Gen Energy SVA (£/MWh) 0.011 0.012 0.014
Main Charges
Energy fee (£/MWh) 0.08501 0.07783 0.09421

 

Table 12

Cost recovery by charging item
Charge Item 2020/21
(£M)
2020/21
% of Total
Specified Charges
CVA BM Units 0.0%
SVA Base BM Units 0.0%
SVA Additional BM Units 0.1 0.2%
Data Line 0.5 0.9%
Comms Software (total) 0.4 0.7%
Contract Traded 0.8 1.4%
CVA Metering Systems 0.6 1.0
Membership Fee 1.3 2.4%
SVA
SVA Metering Systems (£/msid/month) 3.5 6.3%
Gen Energy SVA (£/MWh) 3.5 6.3%
Main Charges
Energy fee (£/MWh) 45.1 80.9%
Main Charges 55.8 100%